Why is one toilet per 20 workers the wrong number to plan with?
Because it is not what the standard says. The table in 29 CFR 1926.51(c)(1) gives one toilet facility for 20 or fewer workers, then one toilet seat and one urinal per 40 workers above that, and one seat and one urinal per 50 at 200 or more. A contractor-guide figure of one per 20 does not match it.
The shorthand is wrong in both directions, which is why it survives. On a crew of 25 it over-provides and nobody complains; on a crew of 120 it quietly turns into the wrong arithmetic, because the standard counts seats and urinals rather than cabins, and because the ratio changes again at the top band. A site sized from the shorthand has no defensible answer when asked which part of the table it was following.
There is also a drafting quirk worth knowing: the printed tiers overlap at 20 workers, so the boundary is genuinely ambiguous in the table as published. The practical response is not to build a plan that depends on it. Work from the band the crew is clearly inside, and where a crew is sitting right on the line, provide for the heavier reading.
Can a unit that is on site stop satisfying the requirement?
Yes. An OSHA interpretation from 2006 takes the position that an unsanitary toilet is not a toilet that has been provided. A cabin standing on the ground in an unusable state is not doing the job the standard asks for, however it looks on a delivery note.
That reframes servicing as part of compliance rather than a comfort item, and it has a practical consequence for how a site buys the service. The interval has to be set against the crew that is actually using the unit, and revisited when the headcount changes, a second shift starts, or the work moves somewhere hotter and harder. A every two weeks run on a crew that has tripled is not servicing.
It also means the paperwork a superintendent keeps is worth something. Knowing when each unit was last serviced, and by whom, is the difference between a defensible arrangement and an argument. In Ohio the hauler side keeps records for at least five years, so the information exists; the site just has to ask for it.
Who is allowed to take the waste off an Ohio job site?
A registered septage hauler. Ohio's sewage rules put portable toilets alongside privies and holding tanks, with the owner having a registered hauler remove the contents before capacity is exceeded; haulers register with the board of health and each vehicle carries a board of health permit for its category of work.
There is a second registration on top of that for anyone discharging at the city plant. The Toledo municipal code requires domestic septage haulers to register with the City of Toledo's Division of Water Reclamation, post a bond and display an annual decal renewed each year, and loads at the plant's septic disposal building are sampled and can be refused. No fee, bond amount or deadline is published on this page, because none was sourced for it.
Where septage is land applied instead, that needs a board of health permit and follows the federal sludge regulations. None of this is a claim about any particular provider; it is the framework the hauling side of this trade operates inside, and it is the reason a job-site unit is not something a crew empties for itself.
Do construction-site units need to be accessible?
Where only construction personnel use a cabin on a construction site, the Access Board's guide puts it outside the accessible-unit section of the 2010 ADA Standards and outside the accessible-route requirement. The exemption is about who uses the unit, not about where it stands.
So the test is the user group. A cabin inside the fence for the trades falls under the exemption; a unit placed for visitors, for an open day, for a public viewing area or for anyone who is not construction personnel does not, and the cluster rule applies to it. Mixed-use arrangements are the ones that catch sites out, because the exemption is read as a site-wide allowance when it is not.
Where the cluster rule does apply, write it carefully: about 5 percent of units at each cluster, with a minimum of one often cited. The published wording differs between copies of the standards, and a 1993 Department of Justice letter describes an older approach, so the provider confirms the count rather than a page like this one asserting it.
What moves the price of a job-site rental up or down?
Crew size and the count it drives, how long the unit stays, servicing frequency, unit type, whether handwashing is included, how often units have to move with the work, and how easily a service truck can reach the placement. The provider explains and approves the price before anything is delivered.
On a long job the servicing frequency, not the cabin, is the lever: a unit standing for eight months costs what its service runs cost. That is also where a change in crew size shows up, because the interval is tied to the headcount rather than to the calendar. Sites that review the count at each phase usually end up paying for what they are actually using, and the cost drivers are set out separately.
Access and relocation are the other two. A placement a truck can pull alongside is a different job from one reached across a built-up site, and a unit that moves with a corridor crew is a series of placements rather than one. Which state the site is in matters as well, since Ohio and Michigan license the hauling side differently. No figure for any of this is published here.